Jones, D. A.; Eckert, C. M. and Gericke, K.
(2018).
DOI: https://doi.org/10.21278/idc.2018.0520
Abstract
This paper categorises and describes the design stages, stakeholders and decision processes of an overcapacity boiler upgrade that came about from the excessive use of design margins. Using a hospital case study, the reason behind the overcapacity and excessive margins is explored using semi-structured interviews, document analysis and process modelling. Design margins arise from a lack of systemic thinking during the design and installation phases. It is likely that margins are added as a matter of habit
with no real thought to their applicability, calling into question the design process.